Tag Archive: New Base

New Base Progress – May 2018

Yesterday Wasdale MRT accepted handover of their purpose-built new base from principal contractor Roland Hill Ltd. Some fitting out and testing of communications by the team is required prior to going operational in July.

Thank you to all in the community who have supported this project and are instrumental in achieving this important milestone.

Here …

Continue reading »

Permanent link to this article: http://www.wmrt.org.uk/2018/05/new-base-progress-may-2018/

New Base Progress – April 2018

April has seen the building nearing completion. Progress continues with plastering, painting, cabling, fitting of doors, doorframes, stairs and the myriad of jobs to make the base useable.  The kitchen is in the final stages of fit out. The radio mast has been fitted with aerial and cabling. Early in April, the vehicles were parked …

Continue reading »

Permanent link to this article: http://www.wmrt.org.uk/2018/04/new-base-progress-april-2018/

New Base Progress – March 2018

March has seen a huge amount progress with plaster boarding, cabling, plastering, the laying of the concrete floor, the commissioning of the garage doors and the ground source heat pump. The kitchen has been fitted out as have both bath rooms and the communications installation is in progress.

 

Permanent link to this article: http://www.wmrt.org.uk/2018/03/new-base-progress-march-2018/

New Base Progress – February 2018

A lot has happened in February. Here are some pictures showing the concrete apron, the garage doors, and some of the fit out inside including the ground source heat pump. The training room has been plastered as well as several other areas.

 

Permanent link to this article: http://www.wmrt.org.uk/2018/02/new-base-progress-february-2018/

New Base Progress – January 2018

After the joists were installed, the fit out of the interior of the base is underway. The individual rooms are now taking shape and the garage is due to be concreted soon. The radio mast is ready for antennae and cabling.

 

Permanent link to this article: http://www.wmrt.org.uk/2018/01/new-base-progress-january-2018/

New Base Progress – December 2017

The month of December saw the completion of the external blockwork and the installation of the ceiling joists. We also took delivery of and erected the new radio mast. The building is almost watertight and the next steps are to fit the door and window furniture.

Permanent link to this article: http://www.wmrt.org.uk/2018/01/new-base-progress-december-2017/

New Base Progress – November 2017

This month saw significant effort on the block work and cladding. Also, the radio mast was delivered and installed on its foundation. At the end of the month the floor joists were delivered.

Permanent link to this article: http://www.wmrt.org.uk/2017/12/new-base-progress-november-2017/

New Base Progress – October 2017

October has seen the roof sections installed along with cladding and block work. The ground source heat pump manifold has been connected. The last few pictures show the view from inside the building for the first time, with the two garage openings visible, gear-up room, control room, lobby, office, wet room, drying room and plant …

Continue reading »

Permanent link to this article: http://www.wmrt.org.uk/2017/10/new-base-progress-october-2017/

New Base Progress – September 2017

Following the completion of the ground preparation last month, September has seen significant progress above ground. Here you can see that the steel frame has been erected and that the block work has started. The garage entrances are now visible nearest the camera and some of the cladding has been delivered to site.

Permanent link to this article: http://www.wmrt.org.uk/2017/10/new-base-progress-september-2017/

New Base Progress – August 2017

The new base now has an electricity supply and drainage. Steel work is due to arrive on site very soon and the construction above ground level can then begin.

Permanent link to this article: http://www.wmrt.org.uk/2017/09/new-base-progress-august-2017/

Page 1 of 212